INFO EXHIBIT # | DESCRIPTION | |
I-001 | Opening Statement of William Wells, Hydro President | |
I-002 |
Excerpt from CA11 Hydro's 2000 Annual Report - p.4 |
|
I-003 |
Excerpt from CA101 Hydro' s 1998 Annual Report - p.4 |
|
I-004 |
Excerpt from NP-24 re Newfoundland and Labrador Hydro's 1999, 2000 and 2001 Operating and Capital Budgets(s) Submissions to the Minister of Mines and Energy |
|
I-005 | Listing - Oral Presentations - Public Participation Days | |
I-006 |
The Role of Independent Counsel to the Tribunal: Advising the Tribunal - Richard Steinecke |
|
I-007 |
British Columbia Utilities Commission The Public Hearing Process - why we have public hearings and how to participate |
|
I-008 |
National Energy Board The Public Hearing Process |
|
I-009 | Exhibit LBB-4, Page 1 of 1 | |
I-010 |
Excerpt - Schedule 1.2, Page 1 of 6, Exhibit JAB-1 Rev. 1 Page: 3 of 94 - 30 Sep 2001 |
|
I-011 |
Excerpt - Schedule VIII Revised H. G. Budgell Newfoundland and Labrador Hydro - Demand and Energy Requirements Forecast 2001 - 2010 Total Island Interconnected System |
|
I-012 | Comparison of Budget and Actual Capital Expenditures of Newfoundland & Labrador Hydro - 1992-2000 | |
I-013 | Newfoundland and Labrador Hydro - Existing VHF Repeater and Trunking Facilities - Figure A2 | |
I-014 | Excerpt Schedule 1A - J.C. Roberts pp 4 - October 31, 2001 | |
I-015 | Excerpt from Board Order No. P.U. 31 (2000-2001) pp 1, 4 and 5 | |
I-016 |
Excerpt from 1993 Generic Cost of Service Report of the Board to the Minister of Mines and Energy p74 - PART III - SUMMARY OF RECOMMENDATIONS |
|
I-017 | JDEdwards Presentation Enterprise Resource Planning (ERP) | |
I-018 | Excerpt from PU 7 (1996-97) | |
I-019 | Excerpt from PU 36 (1998-99) | |
I-020 | Excerpt from 1992 PUB Report to Minister - page 85 | |
I-021 | Statement of Counsel - II |