Application for Capital Expenditures for the Purchase and Installation of Bay d’Espoir Unit 8 and Avalon Combustion Turbine - 2025-05-09
Schedule 1: Overview
• Appendix A: Lessons Learned Overview
• Appendix B: Governing Bodies Overview
• Appendix C: Major Projects Team Overview
• Appendix D: Planned Project Budget Rate Impact Analysis
• Attachment 1: Governance Framework
• Attachment 2: Addendum to 2020 Hydrology Study
Schedule 2: Settlement Agreement
Schedule 3: Expansion Plan Update
• Appendix A: 2024 Load Forecast Report
Schedule 4: Bay d’Espoir Unit 8 Project Evidence
• Appendix A: Project Budget Breakdown
• Appendix B: Critical Path Schedule
• Appendix C: Engagement Summary
• Attachment 1: Basis of Estimate
• Attachment 2: Basis of Schedule
Schedule 5: Avalon Combustion Turbine Project Evidence
• Appendix A: Construction Work Packages
• Appendix B: Project Budget Breakdown
• Appendix C: Critical Path Schedule
• Appendix D: Engagement Summary
• Attachment 1: Basis of Estimate
• Attachment 2: Basis of Schedule