P.U.  21 (2001-2002)

 

 

 

 

IN THE MATTER OF the

Public Utilities Act, (“the Act”)

   

                  AND

 

IN THE MATTER OF an amended application by

Newfoundland Power Inc. (the “Applicant”) for an

Order pursuant to Sections 38, 41, 78 and 80 of the Act:

(a)  approving its 2002 Capital Budget;

(b)  (i) fixing and determining its average rate base for 2000 in

the amount of $520,979,000; (ii) approving its revised forecast average rate base for 2001 in the amount of $541,496,000; and (iii) approving its forecast average rate base for 2002 in the amount of $562,983,000;

(c)  approving revised values for rate base and invested capital

      for use in the automatic adjustment formula (the “Automatic Adjustment Formula”) for the calculation of return on rate base for 2002 pursuant to Orders No. P.U. 16 and 36

      (1998-99), No. P.U. 18 (1999-2000) and P.U. 24 (2000-2001);

            and

(d)  consenting to the relocation of a gas turbine generator (“the

      Generator”)

 

 

            WHEREAS Section 41 of the Act requires that a public utility shall submit an annual capital budget of proposed improvements or additions to its property to the Board of Commissioners of Public Utilities (the "Board") for its approval not later than the 15th day of December in each year for the ensuing calendar year; and

 

            WHEREAS Section 78 of the Act provides that the Board may fix and determine the rate base of a public utility; and

 

            WHEREAS Section 80 of the Act provides a public utility is entitled to earn annually a just and reasonable return on rate base as approved by the Board; and

 

WHEREAS Section 38 of the Act requires that the written consent of the Board to discontinue a service shall only be given after notice is provided to an incorporated municipal body interested, and after there has been an inquiry; and

 

            WHEREAS by registered mail dated August 20, 2001 the Board gave notice to those incorporated municipalities which may be affected by the Applicant’s request to relocate the Generator from Salt Pond on the Burin Peninsula to Wesleyville Substation in Bonavista North; and

 

            WHEREAS the Board has received no representations opposing the Applicant’s request to relocate the Generator from Salt Pond to Wesleyville Substation; and

 

            WHEREAS in Orders No. P.U. 16 and 36 (1998-99), the Board provided for an automatic adjustment formula to adjust rates annually based upon variations in the rate of return on rate base; and

 

            WHEREAS the Applicant submitted its original application on August 14, 2001 and submitted an amended application on September 4, 2001 and on September 6, 2001 the Board conducted a public hearing to consider the application in its Hearings Room in St. John's; and

 

            WHEREAS the Board requested additional information of the Applicant with respect to the matters contained in the application which information was provided to the Board by the Applicant; and

 

            WHEREAS the Board retained the firm of Grant Thornton LLP to review the application and schedules and calculations contained therein; and

 

            WHEREAS William Brushett, C.A., of Grant Thornton LLP filed an affidavit with the Board attaching the report (“Grant Thornton Report”) of their review; and

 

            WHEREAS the Grant Thornton Report confirmed the calculations in the application, including the calculations of forecast rate base and invested capital to be used in the automatic adjustment formula, and that the calculations are in accordance with P.U. 36 (1998-99) and P.U. 18 (1999-2000); and

 

            WHEREAS the Applicant was represented by Gillian Butler, Q.C. and Peter Alteen, Counsel to the Applicant; and

 

            WHEREAS evidence in support of the application was presented by the following management of the Applicant: Philip Hughes, President and Chief Executive Officer; Barry Perry, Vice-President, Finance and Chief Financial Officer; Earl Ludlow, Vice-President, Operations and Engineering; Nora Duke, Vice-President Customer and Corporate Services; and Peter Collins, Manager, Information Services; and

 

            WHEREAS the evidence in support of the application provided details of the Applicant’s proposed 2002 Capital Budget; its 2000 rate base; and its forecast average rate base and average invested capital for 2001 and 2002; and

 

            WHEREAS Mark Kennedy was present as Counsel to the Board; and

 

WHEREAS the Board has carefully considered all the evidence and comments.

 

 

 

IT IS THEREFORE ORDERED THAT:

 

 

1.      The Applicant's capital budget in the amount of $54,619,000 as set out in Schedule A hereto is hereby approved.

 

2.      The Applicant's proposed 2002 capital expenditures as set out in Schedule B hereto are hereby approved.

 

3.      The Applicant’s rate base for the year ending December 31st, 2000 be hereby fixed and determined at $520,979,000.

 

4.      The Applicant’s forecast average rate bases for the year ending December 31st, 2001 of $541,496,000 and for the year ending December 31st, 2002 of $562,983,000 are hereby approved.

 

5.      The use of the forecast average rate base for 2002 of $562,983,000 and the forecast average invested capital for 2002 of $626,870,000 be approved for the purpose of calculating allowed return on rate base for 2002 using the automatic adjustment mechanism pursuant to Orders No. P.U. 16 and 36 (1998-99).

 

6.         The Applicant will present to the Board, in conjunction with the 2003 Capital Budget application, an up-to-date status report on the 2002 capital expenditures showing, for each project,

            i)          the approved budget for 2002,

            ii)         the expenditures prior to 2002,

            iii)         the expenditures to the date of the application in 2002,

            iv)        the expected remaining expenditures in 2002,

            v)         the variance between the expected total expenditures and the approved budget, and

            vi)        an explanation of the variance.

 

7.         The Applicant will present an annual report to the Board on its capital expenditures within sixty (60) days after the end of the year 2002.

 

8.         Consent is hereby given for the Applicant to relocate the Generator from its current location at Salt Pond on the Burin Peninsula to the Applicant’s Wesleyville Substation in Bonavista North.

 

9.         All costs and expenses of the Board incurred in connection with the Application shall be borne by the Applicant.

 


                                                                                   

DATED at St. John’s, Newfoundland this 21st day of September 2001

 

 

 

 

                                                                                                                                                           

 

 

                                                                                    ______________________________

                                                                                    Darlene Whalen, P.Eng.,

Vice-Chairperson.

 

 

                                                                                                                                               

                                                                                    Raymond A. Pollett,

                                                                                    Commissioner.

 

                                                                                               

                                                                                                                                               

                                                                                    John William Finn, Q.C.,

                                                                                    Commissioner.

 

 

 

__________________________

G. Cheryl Blundon,

Board Secretary.

Orders / Home