Newfoundland and Labrador Hydro
New Transmission Line Corridor from Bay d'Espoir
to Western Avalon


The documents provided are for informational purposes only and are NOT the Official Board Record. Please read the Board Disclaimer before reviewing any information on this site.


Application
     New Transmission Line Corridor from Bay d'Espoir to Western Avalon
Notices
     May 8, 2014 ~ Notice of Application - New Transmission Line Corridor from
   Bay d'Espoir to Western Avalon

Correspondence
     June 5, 2014 ~ Anemos Energy - Intervenors Submission
   June 5, 2014 ~ CA - Intervenor Submission
   June 5, 2014 ~ Danny Dumaresque - Intervenor Submission
   June 5, 2014 ~ IC - Intervenor Submission
   June 5, 2014 ~ Newfoundland Power - Intervenor Submission
   June 5, 2014 ~ Vale - Intervenor Submission
   June 27, 2014 ~ To Parties - Filing Schedule for RFIs
   Oct 15, 2014 ~ To Parties - Setting Remaining Schedule
   Oct 20, 2014 ~ IC - No Comments
   Oct 20, 2014 ~ NP - No Comments
   Oct 20, 2014 ~ DD - No Comments
   Oct 23, 2014 ~ CA - No Comments
   Oct 23, 2014 ~ To Parties - Remaining Schedule
   Oct 31, 2014 ~ NP - Submission
   Nov 5, 2014 ~ CA - Written Submission
   Nov 5, 2014 ~ IC - Submission
   Nov 5, 2014 ~ Vale - Comments
   Nov 10, 2014 ~ NLH - Final Submission
RFI Questions
     July 17, 2014 ~ IC-NLH-1 - IC-NLH-14: Questions Only
   July 17, 2014 ~ PUB-NLH-1 - PUB-NLH-68: Questions Only
   July 17, 2014 ~ CA-NLH-1 - CA-NLH-20: Questions Only
   July 17, 2014 ~ DD-NLH-001 - DD-NLH-010: Questions Only
   July 17, 2014 ~ NP-NLH-001 - NP-NLH-012: Questions Only
Replies to RFI's
     Public Utilities Board - Requests
   Industrial Customers - Requests
   Consumer Advocate - Requests
   Newfoundland Power - Requests
   Danny Dumaresque - Requests
Board Orders
     December 12, 2014 ~ PU 53 (2014)
 

PUB Home Page

Any questions, problems or comments concerning this page,
please contact
webmaster@pub.nl.ca