NLH - Request for Filing of Application for 2015 Interim Rates
January 2015
  |  
 |  
 | 
 
 | 
 
 | 
|  
 | 
 January 12
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Request for Comments - Nunatsiavut Government Intervenor Submission
 
February 2015
  |  
 |  
 | 
 
 | 
 
 | 
 
|  
 | 
 
February 23
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Request for Revisions to Responses to RFIs
  |  
  |  
 | 
 
February 25
  | 
 
 |  
 | 
 Public Utilities Board
 
        
PUB-NLH-359 - PUB-NLH-450: Questions Only
  | 
March 2015
  |  
 |  
 | 
 
 | 
 
 | 
|  
 | 
 
March 20
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Request Comments Hydro's letter of March 13, 2015 to strike certain Rfis from the record
  | 
April 2015
  |  
 |  
 | 
 
 | 
 
 | 
|  
 | 
 
April 14
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Public Utilities Board RFIs: PUB 451 - 483 NLH: Questions Only
  | 
|  
 | 
 
April 15
  | 
 
 |  
 | 
 Public Utilities Board
 
        
PUB 484 NLH: Question Only
  | 
May 2015
  |  
 |  
 | 
 
 | 
 
 | 
|  
 | 
 
May 7
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Motions Day
  | 
|  
 | 
 
May 8
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Geoff Young - Delay in Filing 2nd Round Responses to RFIs
  | 
|  
 | 
 
May 13
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Motions Day Deferred
  | 
|  
 | 
 
May 22
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Request for Comments - Delay in Filing Innu Nations RFIs
  | 
|  
 | 
 
May 26
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Request for Comments on Innu Nations RFI filing date and proposed schedule
  | 
|  
 | 
 
May 29
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Schedule - Vale - Application for an Order Compelling NLH to Fully Respond to Certain RFIs
  | 
|  
 | 
 
May 29
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Innu Nations schedule
  | 
June 2015
  |  
 |  
 | 
 
 | 
 
 | 
|  
 | 
 
June 1
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Schedule Changes Prefiled Evidence
  | 
|  
 | 
 
June 1
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Expert Report - John Wilson
  | 
|  
 | 
 
June 1
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Expert Report - Brad Rolph
  | 
|  
 | 
 
June 4
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Enclosing Boards Expert Reports
  | 
|  
 | 
 
June 5
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Revised Schedule - Vale's Application for an Order Compelling NLH to Fully Respond to Certain RFIs
  | 
|  
 | 
 
June 10
  | 
 
 |  
 | 
 Newfoundland and Labrador Hydro
 
        
To Parties - Revised Schedule Vale's Application
  | 
|  
 | 
 
June 11
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Expert Reports - Grant Thornton and Liberty Consulting
  | 
|  
 | 
 
June 12
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Enclosing - Grant Thornton Report
  | 
|  
 | 
 
June 15
  | 
 
 |  
 | 
 Public Utilities Board
 
        
PUB-CA-3 - 4: Questions Only
  | 
|  
 | 
 
June 15
  | 
 
 |  
 | 
 Public Utilities Board
 
        
PUB-V-1 - 3: Questions Only
  | 
|  
 | 
 
June 15
  | 
 
 |  
 | 
 Public Utilities Board
 
        
PUB-IC-6 - 17: Questions Only
  | 
|  
 | 
 
June 15
  | 
 
 |  
 | 
 Public Utilities Board
 
        
PUB-NP-8 - 10: Questions Only
  | 
|  
 | 
 
June 23
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Grant Thornton 2013 Hydro Annual Financial Review
  | 
July 2015
  |  
 |  
 | 
 
 | 
 
 | 
|  
 | 
 
July 7
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Liberty Consulting Group Prudence Review of Newfoundland and Labrador Hydro and Review Schedule
  | 
|  
 | 
 
July 10
  | 
 
 |  
 | 
 Public Utilities Board
 
        
PUB-NLH-485 - PUB-NLH-488: Questions and Setting Further RFI Schedule
  | 
|  
 | 
 
July 29
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To - Parties - RFI-V-NLH-125 Response Date
  | 
|  
 | 
 
July 31
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To - Parties - Innu Nation Address Change
  | 
August 2015
  |  
 |  
 | 
 
 | 
 
 | 
|  
 | 
 
August 19
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Notice of Hearing-Invitation for Public Participation
|  
 | 
 
August 21
  | 
 
 |  
 | 
 Public Utilities Board
 
        
Parties' Settlement Agreement
November 2015
  |  
 |  
 | 
 
 | 
 
 | 
 
|  
 | 
 
November 19
  | 
 
 |  
 | 
 Public Utilities Board
 
        
To Parties - Final Written Submission
 
   January 2016  | 
    | 
    | 
    | 
    
 |  
    |   | 
     January 18   | 
      | 
      | 
    Public Utilities Board 
               To Parties - Issues for Oral Submissions  
      
      |    |    |    |