01/16/24 |
NLH |
Deferrals, accounts, and reserves |
Application by
Newfoundland and Labrador Hydro for approval
of amendments to the Holyrood Thermal
Generating Station Accelerated Deferral
Account approved in Order No. P.U. 4(2022). |
|
01/18/24 |
NP |
Capital Budget |
Application by
Newfoundland Power Inc. for an Order pursuant
to sections 41 and 78 of the Act: (a) approving its
2024 Capital Budget; (b) providing approval to
proceed with the construction, purchase or lease of
improvements or additions; and (c) fixing and
determining its average rate base for 2022. |
|
01/26/24 |
NP |
Contribution in Aid of Construction |
Application by Newfoundland Power Inc. for approval of a Contribution in Aid of Construction to provide single-phase electrical service for roadway lighting in the City of St. John's, pursuant to section 41 of the Act. |
|
01/26/24 |
NLH |
Rates |
Application by Newfoundland and Labrador Hydro for approval of
Island Industrial Customer rates to (i) reflect revisions
with respect to the Island Industrial Customer Rate
Stabilization Plan Adjustments, and (ii) implement a Project Cost Recovery Rider. |
|
01/30/24 |
NP |
General Rate Application |
General rate application
by Newfoundland Power Inc. to establish
customer electricity rates based on costs for
the 2025-2026 period. |
|
02/09/24 |
NP |
Contribution in Aid of Construction |
Application filed by Newfoundland Power Inc. in accordance with Order No.
P.U. 4(1997-98) to update the cost factors used
in its Contribution in Aid of Construction policy. |
|
03/07/24 |
NLH |
Contribution in Aid of Construction |
Application by Newfoundland and Labrador Hydro for
approval of a contribution towards the cost
of improvements for Braya Renewable Fuels (Newfoundland) GP Inc., pursuant to section
41(5) of the Act. |
|
03/07/24 |
NLH |
Contribution in Aid of Construction |
Application by Newfoundland and Labrador Hydro for
approval of a contribution towards the cost
of improvements for Vale Newfoundland and Labrador Limited, pursuant to section
41(5) of the Act. |
|
03/07/24 |
NLH |
Contribution in Aid of Construction |
Application by Newfoundland and Labrador Hydro for approval of a Contribution in Aid of Construction to provide single-phase electrical service to the Department of Transportation and Infrastructure for a highway depot, pursuant to section 41 of the Act. |
|
03/13/24 |
NP |
Capital Budget |
Application by
Newfoundland Power Inc. for an Order pursuant
to sections 41 and 78 of the Act: (a) approving its
2024 Capital Budget; (b) providing approval to
proceed with the construction, purchase or lease
of improvements or additions; and (c) fixing and
determining its average rate base for 2022. |
|
04/03/24 |
NLH |
Deferrals, accounts, and reserves |
Application by Newfoundland and Labrador Hydro for recovery of the 2023 balance in the Isolated Systems Supply Cost Variance Deferral Account pursuant to sections 70(1) and 80 of the Act. |
|
04/10/24 |
NP |
Deferrals, accounts, and reserves |
Application by
Newfoundland Power Inc. for approval of
the balance in the Weather Normalization
Reserve as of December 31, 2023 pursuant to sections 69(3) and 78 of the Act. |
|
04/10/24 |
NP |
Deferrals, accounts, and reserves |
Application by Newfoundland Power Inc. for approval of the disposition of the 2023 balance in the Demand Management Incentive Account pursuant to sections 58 and 80 of the Act. |
|
04/25/24 |
NLH |
Contribution in Aid of Construction |
Application by Newfoundland and Labrador Hydro for
approval of a contribution towards the cost
of improvements from Iron Ore Company of Canada, pursuant to section 41(5) of the Act. |