CONSENTS

   
Consent #      Description
     
Consent # 1   October 18, 2004
Settlement Report of agreement regarding certain capital projects as proposed by NLH
     
     

 

UNDERTAKINGS

   
Undertaking #      Description
     
U Hydro # 1   October 6, 2004
Requested by Industrial Customers of TRO Panel
     - Transcript October 6, 2004 - pg. 126
Please explain why there is $19,872 for the year 2005 under the column “Operator” in the “Retire Plant” alternative in the analysis on page 2 of IC-18NLH.
     
U Hydro # 2   October 6, 2004
Requested by Industrial Customers of TRO Panel
     - Transcript October 6, 2004 - pg. 127
Please explain the $13,113 under the column “Capacity” commencing in year 2011 for the “Retire Plant” alternative in the analysis on page 2 of IC-18NLH.
     
U Hydro # 3   October 6, 2004
Requested by Industrial Customers of TRO Panel
     - Transcript October 6, 2004 - pg. 134
Provide a breakdown of the projects included in B-103
     
U Hydro # 4   October 6, 2004
Requested by Industrial Customers of TRO Panel
     - Transcript October 6, 2004 - pg. 148
Re: criteria for light duty mobile equipment – Are there any additions to mobile equipment fleet associated with this $260,000 or is this all replacement?
Verbal Reply: Transcript October 7, 2004 Page 7
     
U Hydro # 5   October 6, 2004
Requested by Industrial Customers of TRO Panel
     - Transcript October 6, 2004 - pg. 150
Are there any new allocations of light duty vehicles associated with Project A-8 for $260,000
Verbal Reply: Transcript October 7, 2004 Page 7-8
     
U Hydro # 6   October 6, 2004
Requested by Industrial Customers of TRO Panel
     - Transcript October 6, 2004 - pg. 180
Re: reconciliation of B-83 from last year with B-147 from this year, relating to vehicles and the average age of the vehicles being replaced
Verbal Reply: Transcript October 7, 2004 Page 72-75
     
U Hydro # 7   October 6, 2004
Requested by Industrial Customers of TRO Panel
     - Transcript October 6, 2004 - pg. 190
Re: transmission line work being done for 2005 under the wood pole management program – identify the lines that are going too be replaced in the first year of those 4000 poles.
Verbal Reply: Transcript October 7, 2004 Page 75
     
U Hydro # 8   October 7, 2004
Requested by Industrial Customers of TRO Panel
     - Transcript October 7, 2004
Please explain how the $13,113 under the column “Capacity” commencing in year 2011 for the “Retire Plant” alternative in the analysis on page 2 of IC-18NLH is calculated. Similarly, explain how the $45,895 under the column “Capacity” in year 2011 for the “Retire Plant in 2006: of the Snook’s Arm Penstock Replacement Analysis is calculated.
     

 

EXHIBITS

   
Exhibit #      Description
     
FM/GH # 1   October 6, 2004
Slide Presentation By Hydro
Transmission and Rural Operations
     
JRH # 1   October 7, 2004
Slide Presentation By Hydro
Production
     
GD # 1   October 8, 2004
Slide Presentation By Hydro
Hydro's VHF Mobile Radio System Replacement
     

 

INFORMATION

   
Information #      Description
     
Information # 1   October 10, 2004
Grant Thornton: NLH 2003 Average Rate Base
     

 